Single Storey Extension Quote Breakdown (UK Template)

Extension quotes win on clarity. Stage the job in build order, price each stage, and list exclusions properly. That's what makes a client trust a five-figure number.

Write yours free, no account

Rough notes in, finished quote out. 2 free goes.

Worked example

The notes

Mr & Mrs Okafor, Whitley Bay: “Rear kitchen extension 4m × 5m, strip foundations, cavity walls, flat roof with 2 rooflights, steel for knock through, first fix, plaster. 10 weeks.”

ItemQtyUnit priceTotal
Groundworks and foundations1 stage£6,200.00£6,200.00
Superstructure: cavity walls to wall plate1 stage£9,400.00£9,400.00
Flat roof and 2 rooflights1 stage£5,600.00£5,600.00
Steel and knock through1 stage£3,200.00£3,200.00
First fix electrics and plumbing1 stage£3,600.00£3,600.00
Plastering1 stage£2,400.00£2,400.00
Subtotal
£30,400.00
VAT at 20%
£6,080.00
Total
£36,480.00

Example prices for illustration only. Your prices depend on your area, the spec and access, so set your own.

Turn your own notes into a quote like this

Type the job how you'd say it. Workscribe lays it out, prices each line and works out the VAT. Free to try, no account.

Try it free

What a single storey extension quote should include

  • Stages in build order with a price each
  • Size, specification and what the client supplies
  • Exclusions: planning, building control fees, engineer, party wall
  • Programme in weeks
  • Staged payments tied to completed work
  • Contingency and how variations are handled

Common mistakes

No stage payments

Never fund a client's extension yourself. Tie payments to completed stages.

Thin exclusions

Ground conditions, services and building control fees should be listed so they don't land on you.

Questions

How do I break down an extension quote?

+

Stage it in build order: groundworks, superstructure, roof, first fix, plastering, second fix, finishes. Price each.

Should I include a contingency?

+

Many builders add a stated percentage for unknowns, especially below ground. Explain what it covers.

What's commonly excluded?

+

Planning and building control fees, structural engineer, party wall costs and anything the client supplies.

General guidance, not legal or technical advice. Check current regulations for your job.