Builder's Weekly Client Update Email Template (UK)

Clients ring because they don't know what's happening. One short update every Friday answers the questions before they're asked: what got done, what's next, what you need from them, and anything that's changed.

Write yours free, no account

Rough notes in, finished update out. 2 free goes.

Worked example

The notes

Mr & Mrs Okafor, Whitley Bay: “Week 4: steel in, roof on and felted, rooflights fitted, first fix electrics done. Next: plumber first fix Mon, plaster Tue-Thu, screed Fri. Rooflights 3 days late, still on track. Need tile choice by Friday.”

Subject: Okafor Residence – Week 4 Update

We're on track for a 10-week completion despite the rooflights arriving three days late. Steel and roof are in, both rooflights are fitted, and first fix electrics are complete.

Completed this week
• Structural steel installed
• Roof on and felted
• Both rooflights fitted
• First fix electrics completed

Coming up next week
• Plumber first fix – Monday 26 October
• Plastering – Tuesday 27 to Thursday 29 October
• Screed – Friday 30 October

Decisions needed from you
• Kitchen floor tile choice – by Friday 30 October
• Confirm socket positions on the island – [confirm deadline]

Anything that's changed
The rooflights were delivered three days late. This has not affected the overall programme, and we remain on schedule for a 10-week completion.

A real update written by Workscribe's free Client Update Writer from the notes above. Check every line before you send yours.

Turn your own notes into a update like this

Type the job how you'd say it. Workscribe lays it out, prices each line and works out the VAT. Free to try, no account.

Try it free

What a weekly client update update should include

  • Subject with the project and the week
  • Two lines on where the job stands
  • Done this week
  • Coming up next week
  • Decisions needed, each with a deadline
  • Delays and their effect on the finish date, stated honestly

Common mistakes

Burying the delay

If something's late, say it in the first three lines. Clients forgive delays; they don't forgive surprises.

Decisions without deadlines

"Pick your tiles" gets ignored. "Tile choice by Friday so we can order" gets answered.

Questions

How often should I update clients?

+

Weekly works for most jobs. Same day each week, so they learn to expect it.

Should I send it by email or text?

+

Email keeps a record of decisions and delays, which protects you if there's ever a dispute.

How long should it be?

+

Short. Under 250 words is plenty.